This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

3D printed reinforced concrete bridge starts to take shape

23 June 2017

The Built Environment department’s concrete printer starts printing the world’s first 3D printed reinforced, pre-stressed concrete bridge.

The printing of concrete for the 3D printed bridge has begun (Credit: TU/e)

The cycle bridge will be part of a new section of ring road around Gemert in which the BAM Infra construction company is using innovative techniques.

One of the advantages of printing a bridge is that much less concrete is needed than in the conventional technique in which a mould is filled. By contrast, a printer deposits only the concrete where it is needed. This has benefits since in the production of cement a lot of CO2 is released and much less of this is needed for printed concrete. Another benefit lies in freedom of form: the printer can make any desired shape, and no wooden moulding frames are needed.

An extra detail is that the researchers in the group of Theo Salet, professor of concrete construction, have succeeded in developing a process to also print the steel reinforcement at the same time. When laying a strip of concrete the concrete printer adds a steel cable so that the bridge is ‘pre-stressed’ so that no tensile stress can occur in the concrete, because this is something that concrete is not able to cope with adequately.

In recent months Theo Salet’s research group made an initial scale model (1:2) and tested its safety by subjecting it to a 2,000kg load. Now that the safety has been demonstrated, a start can be made on printing the concrete elements that will later be glued together to form a bridge. Provincial representative Christophe van der Maat got the ball rolling at TU/e.

It is expected that the bridge elements will be printed and ready within two months. In September the BAM construction company will put the bridge in place in the Noord-Om, a new section of ring road around the village of Gemert, where the company is also using other new innovative building techniques. 