This website uses cookies primarily for visitor analytics. Certain pages will ask you to fill in contact details to receive additional information. On these pages you have the option of having the site log your details for future visits. Indicating you want the site to remember your details will place a cookie on your device. To view our full cookie policy, please click here. You can also view it at any time by going to our Contact Us page.

FAA approves Boeing's redesigned 787 battery system

13 March 2013

The US Federal Aviation Administration (FAA) has approved Boeing's redesigned 787 battery system, after reviewing the company’s proposed modifications.

The certification plan is the first step in the process to evaluate the 787’s return to flight and requires Boeing to conduct extensive testing and analysis to demonstrate compliance with the applicable safety regulations and special conditions.


“This comprehensive series of tests will show us whether the proposed battery improvements will work as designed,” said Transportation Secretary Ray LaHood. “We won’t allow the plane to return to service unless we’re satisfied that the new design ensures the safety of the aircraft and its passengers.”

The battery system improvements include a redesign of the internal battery components to minimise initiation of a short circuit within the battery, better insulation of the cells and the addition of a new containment and venting system.

“We are confident the plan we approved today includes all the right elements to conduct a comprehensive evaluation of the battery system redesign,” said FAA Administrator Michael P. Huerta. “Today’s announcement starts a testing process which will demonstrate whether the proposed fix will work as designed.”

The certification plan requires a series of tests which must be passed before the 787 could return to service. The plan establishes specific pass/fail criteria, defines the parameters that should be measured, prescribes the test methodology and specifies the test set-up and design. FAA engineers will be present for the testing and will be closely involved in all aspects of the process.

The FAA also has approved limited test flights for two aircraft. These aircraft will have the prototype versions of the new containment system installed. The purpose of the flight tests will be to validate the aircraft instrumentation for the battery and battery enclosure testing in addition to product improvements for other systems.

The FAA will approve the redesign only if the company successfully completes all required tests and analysis to demonstrate the new design complies with FAA requirements. The FAA’s January 16, 2013 airworthiness directive, which required operators to temporarily cease 787 operations, is still in effect, and the FAA is continuing its comprehensive review of the 787 design, production and manufacturing process.

The US National Transportation Safety Board interim report on the Boeing 787-8, JA829J, Japan Airlines battery incident is available to read here.